" It is further mutually agreed between the parties hereto that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in... "
Reports of Cases Decided in the Court of Chancery of the State of New Jersey - Stran 248
avtor: New Jersey. Court of Chancery - 1914
Celotni ogled - O knjigi

Reports of Cases at Law and in Chancery Argued and Determined ..., Količina 233

Illinois. Supreme Court - 1908 - 726 strani
...sufficient to indemnify himself against liens or claims against the contractor. Article 10 provided "that no certificate given or payment made under this contract,...performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials." The...
Celotni ogled - O knjigi

Reports of Cases at Law and in Chancery Argued and Determined ..., Količina 274

Illinois. Supreme Court - 1917 - 722 strani
...hereto that no estimates given or payments made under this contract, except the final certificates or final payment, shall be conclusive evidence of...performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials. * *...
Celotni ogled - O knjigi

Reports of Cases at Law and in Chancery Argued and Determined ..., Količina 228

Illinois. Supreme Court - 1908 - 710 strani
...conclusive evidence of performance. Under a building contract providing that no payment or certificate, "except the final certificate or final payment," shall be conclusive evidence of the performance of the contract, the final certificate is conclusive evidence of performance except for fraud or mistake...
Celotni ogled - O knjigi

The Pacific Reporter, Količina 83

1906 - 1148 strani
...signed by said John Parkinson, architect, to the effect that he considers the payment properly due; but no certificate given or payment made under this contract,...performance of this contract either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials." 1....
Celotni ogled - O knjigi

The Pacific Reporter, Količina 61

1900 - 1164 strani
...in article 3 of this contract." "(14) It Is further mutually agreed between the parties hereto that no certificate given or payment made under this contract,...performance of this contract, either wholly or in part, against any claim of the owner, aud no payment shall be construed to be an acceptance of any defective...
Celotni ogled - O knjigi

The Pacific Reporter, Količina 205

1922 - 1152 strani
...follows: "That no certificate given, or payments made under this contract, except the final certificate of final payment, shall be conclusive evidence of the...performance of this contract, either wholly or in part, against any claim of the first party, and that, not until the lapse of thirtyfive days after acceptance...
Celotni ogled - O knjigi

The Pacific Reporter, Količina 133

1913 - 1236 strani
...defend-ant. "Paragraph 18 is as follows : 'It is further mutually agreed between the parties hereto ;lmt no certificate given or payment made ; under this contract, except the final certifi ' cate or final payment, shall be conclusive evidence of the performance of this contract,...
Celotni ogled - O knjigi

The Pacific Reporter, Količina 144

1915 - 1230 strani
...certificates of the architects that they have become due. (10) No certificate given or payment made, except the final certificate or final payment, shall be conclusive evidence of performance either in whole or in part, and no payment shall be construed an acceptance of defective...
Celotni ogled - O knjigi

The Northeastern Reporter, Količina 119

1918 - 1142 strani
...for the same are issued. Article 10. It is further mutually agreed between the parties hereto that no certificate given or payment made under this contract,...performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials. The...
Celotni ogled - O knjigi

The Northeastern Reporter, Količina 39

1895 - 1150 strani
...work upon the performance of which the payment is to become due has been done to his satisfaction.' "No certificate given or payment made under this contract, except the final certificate 01 final payment, shall be conclusive evidence of the performance of this contract, either wholly or...