ment to or acquiescence in the Government's in- terpretation, the Board holds that a disagree- ment with the Govern- ment's interpretation first expressed three months after a problem with internal pipe diam- eters was brought to the contractor's attention by the rejection of a sub- stantial quantity of pipes was untimely and the contractor's claim for a constructive change based on misinterpretation of the contract was denied..
2. Where a contract provision prescribed a method for the repair of airholes in gasket bearing areas of concrete pipe and pro- vided that "All other repairs shall be made in accordance with the pro- cedures of Chapter VII of the Sixth Edition of the Bureau of Reclamation Concrete Manual," and
CONTRACTS-Con.
CONSTRUCTION AND OPERA- TION-Con.
General Rules of Construc- tion-Con.
the Concrete Manual, in addition to prescribing methods of repair, listed nine defects which were normally repairable and where the evidence estab- lished that during con- tract performance the parties considered the Concrete Manual to con- trol not only methods of repair but also the types of repairable defects, re- pair of the listed defects was permissible notwith- standing that the con- tract reference was to "procedures" of the Con- crete Manual and the Government's contention that under the dictionary "procedures" and "meth- ods" have the same meaning...
3. While Federal custom or- dinarily prevails over local usage when in con- flict, in resolving a dis- pute concerning the reasonableness of toler- ances permitted under a contract for the con- struction of a road, state and not Federal custom is held to govern, since the evidence showed state usage to be standardized and the Federal trade practice was not clearly established..
4. Where the Government is obligated to "compen- sate" the contractor for restoring damaged work under a contract provi- sion entitled "Con- tractor's Responsibility for Work," the word
General Rules of Construc- tion-Con.
"compensate" is consid- ered to have a different and more limited mean-
ing than the words "equitable adjustment" used in other provisions of the contract.
Intent of Parties
1. Where the Board found that the contracts contem- plated that repair of listed defects in accord- ance with the Concrete Manual was permissible and the Concrete Manual contained a provision providing that "repairs should not be permitted when the imperfections or damage are the result of a continuing failure to take known corrective action," the Board rules that a reasonable inter- pretation of the quoted provision would permit the denial of otherwise allowable repairs if the defects or damage were attributable to the con- tractor's continued prolonged failure to im- plement measures which the contractor either knows or as a reasonably skilled contractor should know would eliminate or alleviate the defects. The evidence having estab- lished the cause of a particular defect and that the defect occurred in significant numbers of pipes over a substantial period of time, the refusal to permit such defects to be repaired did not con- stitute a change to the
CONTRACTS-Con. CONSTRUCTION TION-Con. Intent of Parties-Con.
contract. The Govern- ment's refusal to permit certain other repairs which the evidence established was based on concern for the integrity of any repair generally rather than the contrac- tor's continuing failure to take known corrective action did constitute a change to the contract... Modification of Contracts 1. A construction contractor's claim for an equitable adjustment is denied where the evidence shows that payment for the overlay work involved in repairing eroded pave- ment was provided for in an accepted change order and the appellant failed to sustain its burden of showing that the straitened financial cir- cumstances in which the
contractor was in at the time of the change order was the result of wrongful action by the contracting officer or other Govern- ment personnel admin- istering the contract un- der which the claim of duress was asserted____- Warranties
1. Under the Standard Form Supply Contract Default clause, a termination for default, following accep- tance, of a contract for the purchase of a scan- ning electron microscope on the grounds it was defective, latently, and by virtue of various
CONTRACTS-Con.
CONSTRUCTION AND OPERA-
breaches of warranty, was improper in the absence of a notice preceding the termination affording the contractor at least ten days within which to cure the defects, and was, accordingly, treated as a termination for the con- venience of the Govern- ment.
DISPUTES AND REMEDIES
Burden of Proof
1. Where the Concrete Manual placed limitations on the repairable area of certain defects and did not limit the repairable area of certain other defects but the evidence established that all such defects were not repairable without regard to magnitude and extent, and the evidence established that repairs normally permitted by the Concrete Manual were not allowed, but evidence of the extent of defects on rejected pipes was lacking, the Board holds that the contractor has failed to carry its burden of proof that pipes were improperly rejected. As to identified pipes which appellant's expert witness testified were re- pairable in accordance with the Concrete Manual, the Board holds that appellant has estab- lished prima facie that the pipes were improperly rejected
2. Where substantial quantities
of pipes which had been
accepted were rejected on
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con. Burden of Proof-Con.
a subsequent inspection, and the evidence did not establish that the pipes did not conform to con- tract requirements, the subsequent rejection of the pipes was improper even though the initial acceptance was not the final acceptance contem- plated by the contract and even though it is a general rule that the bur- den is on the seller to prove that goods re- jected prior to accep- tance conform to contract requirements. The Board holds that the initial acceptance, in the ab- sence of evidence to the contrary, established that the pipes conformed to the requirements of the
3. Where the Government re- fused to allow repairs to certain defects permitted by the Concrete Manual prior to conducting hydro- static tests on the pipes and it appeared that at least some of the pipes would have passed the test and been acceptable if repairs in accordance with the Concrete Man- ual had been allowed, the Government by its ac- tions has made the evi- dence unavailable and the Board utilizes a “jury verdict" approach to de- termine the number of pipes which could have been repaired under the
Concrete Manual and made acceptable_____.
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con.
Burden of Proof-Con. 4. A construction contractor's
claim for an equitable ad- justment is denied where the evidence shows that payment for the overlay work involved in repair- ing eroded pavement was provided for in an ac- cepted change order and the appellant failed to sustain its burden of showing that the strait- ened financial circum- stances in which the con- tractor was in at the time of the change order was the result of wrongful action by the contracting officer or other Govern- ment personnel adminis- tering the contract under which the claim of duress was asserted______
5. A contractor's claim for the cost of repairing a la- goon which was allegedly damaged because a dike not required by the con- tract channeled flood- waters from a rainstorm into the lagoon was denied where the dence did not establish Government responsibil- ity for the existence of the dike, a portion of the damage was attrib- utable to an open sewer trench which was the contractor's responsibil- ity and the evidence did not establish that the dike was a principal causative factor in flood damage to the lagoon. Under the Permits and Responsibilities clause (Article 12 of Standard
Form 23-A, June 1964
DISPUTES AND REMEDIES-Con.
Edition), the contractor is responsible for the work until completion and final acceptance_----
6. Expert testimony giving esti- mates of what would be the cost for a reasonable contractor to restore damage to a road project and to finish the roadway is not accepted where the testimony is unclear and ambiguous respecting the applicable time period, whether all ele- ments of costs and profit are included, and whether the task being estimated was comprehended by the expert----
7. Where a contractor under a
cost-plus-fixed-fee con- tract gave notice of an impending overrun but proceeded with perform- ance without being ad- vised that additional funds had been provided as specified in the Lim- itation of Cost Clause in circumstances where the evidence did not estab- lish that the contractor was directed or induced to continue performance, that there was any under- standing that additional funds would be provided, or that a change to the contract had occurred, the contractor's claim for overrun is denied on the grounds that the con- tractor had proceeded with performance at his own risk and that whether addi- tional funds would be provided was within the
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con.
discretion of the con- tracting officer.
1. Where the Government is
obligated to "compen- sate" the contractor for restoring damaged work under a contract provi- sion entitled "Contrac- tor's Responsibility for Work," the word "com- pensate" is considered to have a different and more limited meaning than the words "equit- able adjustment" used in other provisions of the contract_.
1. Where the Government is obligated to compensate the contractor for resto- ration of damaged work under a contract for road construction and actual costs are in evidence, the contractor's entitlement to compensation is based on recorded actual costs. Liquidated Damages
1. The Board denies a Govern- ment motion for recon- sideration where it finds that a diary entry con- tained in an exhibit offered in evidence by the Government, to- gether with the testimony of a witness for the appellant created an in- ference that the Govern- ment was responsible for an indeterminate portion of a protracted delay in removing utility poles from the work area on a
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con.
Damages-Con.
Liquidated Damages-Con. road construction job and that the Government failed to rebut such in- ference even though in- formation having a direct bearing on the propriety of liquidated damages assessed for delayed per- formance was apparently within its possession or was more accessible to it than it was to the appellant. The Board therefore reaffirmed its prior holdings that no attempt should be made to apportion the delay between the parties and that the contract time should be extended to the date the contract was determined to be substantially complete__
1. Expert testimony giving esti- mates of what would be the cost for a reasonable contractor to restore dam- age to a road project and to finish the roadway is not accepted where the testimony is unclear and ambiguous respecting the applicable time period, whether all elements of costs and profit are in- cluded, and whether the task being estimated was comprehended by the expert...
Equitable Adjustments
1. Where the Government re- quired hydrostatic tests of pipes in excess of those specified by the contracts, the Board rules that the contractor's entitlement to compensation for such
« PrejšnjaNaprej » |