CONTRACTS-Con.
DISPUTES AND REMEDIES-Con. Equitable Adjustments-Con. tests could properly turn on the results of the tests inasmuch as the Inspec- tion and Acceptance Clause of the General Provisions (Standard Form 23-A, April 1961 Edition) allows the Gov- ernment at any time be- fore final acceptance of the entire work to request the removal of completed work at the contractor's expense if the work does not conform to contract requirements and for an equitable adjustment to the contractor if the work does conform to the con- tract...
2. Where the evidence failed to support the contractor's claim as to the amount of extra repair work and testing required by the Government and the quantity of pipe which was improperly rejected and there was substantial evidence that the con- tractor had underbid the work and that a signifi- cant portion of the con- tractor's costs in addition to its estimates was due to factors such as un- proven or unsuitable ma- chinery and equipment, improper maintenance and inexperienced and unskilled labor, justifica- tion for the total cost method of computing an equitable adjustment has not been established. The Board holds that the equitable adjustment due the contractor may prop-
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con. Equitable Adjustments-Con.
erly be computed on the basis of summaries of costs from appellant's
books and records, over- ruling a Government ob- jection to such cost pres- entation made for the first time on brief that the books and records from which the summar- ies were prepared were not available at the hear- ing, since the record re- vealed that appellant had repeatedly offered to
make its records available for audit by the Govern- ment prior to the hearing. 3. A contractor's claim for in- terest as part of an equi- table adjustment was de- nied where there was no evidence of specific loan transactions or of pay- ments of interest in the record....
4. Where the Government is obligated to "compen- sate" the contractor for restoring damaged work under a contract pro- vision entitled "Contrac- tor's Responsibility for Work," the word "com- pensate" is considered to have a different and more limited meaning than the words "equitable adjust- ment" used in other pro- visions of the contract_ _ _ Jurisdiction
1. The Board denied the Gov- ernment's motions to dis- miss as beyond the juris- diction of the Board, the contractor's claims to be compensated for ineffi- ciency resulting from the
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con. Jurisdiction-Con.
interim wrongful rejec- tion of substantial quanti- ties of pipes and for reim- bursement of a sum paid to its subcontractor because of the unavailability of pipe for laying which was allegedly attributable to the Government's in- correct interpretation of the contract as to permis- sible internal diameters of the pipe. On the merits the latter claim was denied, since Government responsibility for payment had not been established.._.
2. A Government motion to dismiss as beyond the jurisdiction of the Board a claim arising out of severe and arbitrary in- spection was denied, the Board holding that such a claim was not readily distinguishable from
claims based upon the imposition of excessive standards of workman- ship which claims are clearly cognizable by the Board as constructive changes. A contractor's claim for lost profits in such circumstances was dismissed as beyond the jurisdiction of the Board since the concept of an equitable adjustment ex- cludes anticipated or un- earned profits on work not accomplished._____
a supply contract which provided for the delivery and installation of a television antenna system did not contain a
CONTRACTS-Con.
DISPUTES AND REMEDIES-Con. Jurisdiction-Con.
"Suspension of the Work" or other "pay for delay" clause and the Government issued a modification postponing the delivery date be- cause the building in which the system was to to be installed had not been completed, the Board dismissed as be- yond its jurisdiction the contractor's claim for costs incurred in main- taining a crew in read- iness to perform the in- stallation inasmuch as the postponement of the de- livery date was not a change within the mean- ing of the "Changes" clause..
Substantial Evidence
1. Expert testimony giving esti- mates of what would be the cost for a reasonable contractor to restore damage to a road project and to finish the roadway is not accepted where the testimony is unclear and ambiguous respecting the applicable time period, whether all elements of costs and profit are in- cluded, and whether the task being estimated was comprehended by the ex-
1. Under the Standard Form Supply Contract Default clause, a termination for default, following accept- ance, of a contract for the purchase of a scan-
1. Under the Standard Form Supply Contract Default clause, a termination for default, following accept- ance, of a contract for the purchase of a scanning electron microscope on the grounds it was defec- tive, latently, and by vir- tue of various breaches of warranty, was improper in the absence of a notice preceding the termina- tion affording the con- tractor at least ten days within which to cure the defects, and was, accord- ingly, treated as a ter- mination for the con- venience of the Govern- ment_
FORMATION AND VALIDITY
Authority to Make
1. The Board denies a construc- tion contractor's claim for the cost of construct- ing a dike which was not a contract requirement where it finds: (i) that the dike was constructed of excess material from a
CONTRACTS-Con.
FORMATION AND VALIDITY-Con. Authority to Make-Con.
sewage lagoon, excava- tion of which was a con- tract requirement; (ii) a reasonable construction of the contract would permit the contracting officer to direct the place- ment of excess material from the lagoon at any place within one-half mile of the site and no part of the dike was in excess of one-half mile from the site; (iii) construction of the dike was not ordered or approved by anyone having authority to com- mit the Government; and (iv) the contractor failed to protest to the con- tracting officer when the alleged extra work was performed...
Cost-Type Contracts
1. Where a contractor under a cost-plus-fixed-fee con- tract gave notice of an impending overrun but proceeded with perform- ance without being ad- vised that additional funds had been provided as specified in the Limita- tion of Cost Clause in circumstances where the evidence did not establish that the contractor was directed or induced to continued performance, that there was any under- standing that additional funds would be provided, or that a change to the contract had occurred, the contractor's claim for overrun is denied on the grounds that the
FORMATION AND VALIDITY-Con. Cost-Type Contracts-Con. tractor had proceeded Page with performance at his own risk and that whether additional funds would be provided was within the discretion of the con- tracting officer.
PERFORMANCE or default
Acceptance of Performance
1. Where substantial quantities of pipes which had been accepted were rejected on a subsequent inspection, and the evidence did not establish that the pipes did not conform to con- tract requirements, the subsequent rejection of the pipes was improper even though the initial acceptance was not the final acceptance contem- plated by the contract and even though it is a general rule that the bur- den is on the seller to prove that goods rejected prior to acceptance con- form to contract require- ments. The Board holds that the initial accept- ance, in the absence of evidence to the contrary, established that the pipes conformed to the require- ments of the contract___ 2. Under the Standard Form Supply Contract Default clause, a termination for default, following accept- ance, of a contract for the purchase of a scanning electron microscope on the grounds it was defec- tive, latently, and by virtue of various breaches of warranty, was im- proper in the absence of a
PERFORMANCE OR DEFAULT-Con. Acceptance of Performance-Con. notice preceding the ter- Page mination affording the contractor at least ten days within which to cure the defects, and was, accordingly, treated as a termination for the con- venience of the Govern- ment....
Excusable Delays
1. The Board denies a Govern- ment motion for recon- sideration where it finds that a diary entry con- tained in an exhibit of- fered in evidence by the Government, together with the testimony of a witness for the appellant created an inference that the Government was re- sponsible for an indeter- minate portion of a pro- tracted delay in removing utility poles from the work area on a road con- struction job and that the
Government failed
to rebut such inference even though information having a direct bearing on the propriety of liqui- dated damages assessed for delayed performance was apparently within its possession or was more accessible to it than it was to the appellant. The Board therefore re- affirmed its prior hold- ings that no attempt should be made to ap- portion the delay between the parties and that the contract time should be extended to the date the contract was determined to be substantially com- plete....
CONTRACTS-Con.
PERFORMANCE OR DEFAULT-Con.
1. Where substantial quantities of pipes which had been accepted were rejected on a subsequent inspec- tion, and the evidence did not establish that the pipes did not conform to contract requirements, the subsequent rejection of the pipes was im- proper even though the initial acceptance was not the final acceptance con- templated by the con- tract and even though it is a general rule that the burden is on the seller to prove that goods re- jected prior to accept- ance conform to contract requirements. The Board holds that the initial ac- ceptance, in the absence of evidence to the con- trary, established that the pipes conformed to the requirements of the contract.
1. Remedies for alleged breach of a private agreement between parties who have conflicting grazing lease applications must be sought in the courts, not in the Department of the Interior, which has no jurisdiction over such matters.
DELEGATION OF AUTHORITY
1. Upon request of the State Director, a District Man- ager, Bureau of Land Management, who has
DELEGATION OF AUTHORITY-Con.
GENERALLY-Con.
authority to enter into timber sale contracts also has authority to ter- minate such contracts when to do so would be in the best interest of the Government.
FEDERAL COAL MINE HEALTH AND SAFETY ACT OF 1969
1. It is error for an Administra- tive Law Judge to fail to to make appropriate find- ings of fact and conclu- sions of law and to show the reasons therefor in his decision in any pro- ceeding brought pursuant to section 109 of the Act (30 U.S.C. § 819) with respect to the occurrence of each violation alleged and as to each of the statutory criteria re- quired by such section to to be considered. Where such findings and con- clusions are merely not labeled or mislabeled the Board will not normally remand; however, where these requisites are ob- fuscated or absent, а remand may be necessary to permit proper adminis- trative and judicial review_
ADMINISTRATIVE PROCEDURE
1. The Board may be persuaded by the findings of fact in an arbitration proceeding where they are made a part of the record, but the Board is not bound or controlled thereby -----
« PrejšnjaNaprej » |